Alice is a senior project manager for a fitness company that is developing a new franchise model. She just led the team through various workshops to capture requirements. What activity is she likely to perform next?
爱丽丝是一家健身公司的高级项目经理,该公司正在开发一种新的特许经营模式。她刚刚带领团队参加了各种研讨会来获取需求。接下来,她可能执行什么活动?
A. Publish requirements management plan 发布需求管理计划
B. Define project scope 定义项目范围
C. Develop work breakdown structure 制定工作分解结构
D. Measure completion of requirements 衡量需求的完成情况
答案:B
爱丽丝刚刚执行了收集需求过程,接下来可能会执行定义范围过程。